McArthur River Mine dredging

McArthur River Mine dredging

Hall was engaged to dredge approximately 200,000m³ of silt and mud from the approach channel at McArthur River Mine’s Bing Bong Station.

Our team mobilised cutter suction dredge Mabuiag to undertake the dredging works and used a booster pump to transfer the dredged material through a 3km pipeline to the existing disposal ponds.

Client: McArthur River Mining (subsidiary of Glencore)

Location: McArthur, NT, Australia

Start Date: December 2012

Completion Date: June 2013